Before you start
Per hour, verification can process 30 orders, picking can process 20 and packing can process 25. Demand is 28 orders per hour. A queue grows before picking.
What to bring
- Per hour, verification can process 30 orders, picking can process 20 and packing can process 25. Demand is 28 orders per hour. A queue grows before picking.
- The case facts and any current policy or rules supplied by your reviewer
- A colleague or faculty reviewer for the retry
Example conversation
A practice conversation
- Fulfilment supervisor
- Should I add another packer to get more orders out?
- Learner
- Picking limits throughput at 20 orders an hour. I would test reducing picking travel, track good units per hour and check whether packing becomes the next constraint.
Work through the case
Map the flow and compare rates
Use good orders per hour in the same period. Under the stated assumptions, picking limits the process to 20 orders per hour before variability and rework. The queue is consistent with that constraint.
Test the reason for lost capacity
Measure interruptions, item travel and stock exceptions at picking. Compare the value of reducing those losses with adding a person elsewhere.
Plan the experiment and watch the next constraint
Test whether staging popular items raises picking throughput. Track output, errors and queues by step. If picking exceeds 25 per hour, packing may become the next limit under the stated rates.
Teachrity voice practice
Rehearse it out loud
- Learner role
- Operations analyst
- AI counterpart
- Fulfilment supervisor
Respond to the brief
Explain the bottleneck and propose an experiment with throughput, quality and queue measures.
Should I add another packer to get more orders out?
What to look for
- Uses consistent rates and identifies the constraint
- Chooses a test aimed at the constraint
- Checks good output and downstream effects
Retry with one change
Picking rises to 26 per hour, but rework also increases. Compare good output and decide whether the change should continue. Use the same rubric to compare both attempts.
Take it into practice
A bottleneck worksheet with capacity, observed rate, queue, proposed experiment and quality guardrail.
Common questions
What if the longest queue is temporary?
Compare repeat periods and actual throughput. A queue may reflect a one-off batch or interruption, so verify the constraint before changing staffing.