Before you start
Two weeks before launch, a stakeholder wants an export screen. Development estimates three days; testing estimates two more. The team can defer an agreed report or move the launch.
What to bring
- Two weeks before launch, a stakeholder wants an export screen. Development estimates three days; testing estimates two more. The team can defer an agreed report or move the launch.
- The case facts and any current policy or rules supplied by your reviewer
- A colleague or faculty reviewer for the retry
Example conversation
A practice conversation
- Department stakeholder
- It is only one screen. Can we just add it without anyone noticing?
- Learner
- The estimate is three days to build and two to test. Can we confirm when users need it? We can trade out the report, move launch, or schedule the export later.
Work through the case
Check the underlying need
Ask why the export is needed, who uses it and the first date it matters. Explore whether a temporary approved workaround addresses the requirement.
Make the full impact visible
Separate coding, sign-off, testing and training. Compare adding now, deferring another deliverable or adding after launch. Show effects on both the launch and current commitments.
Record an authorised choice
Ask the agreed decision-maker to approve the change and updated scope. Document the owner and communicate the decision to people affected downstream.
Teachrity voice practice
Rehearse it out loud
- Learner role
- Project manager
- AI counterpart
- Department stakeholder
Respond to the brief
Present the request and three options in a short decision meeting. Explain which commitment moves under each option.
It is only one screen. Can we just add it without anyone noticing?
What to look for
- Confirms the need before estimating
- Includes full delivery impact
- Records approval and communication
Retry with one change
A compliance dependency makes the export essential for launch. Reassess choices while keeping sign-off and test coverage visible. Use the same rubric to compare both attempts.
Take it into practice
A change note with the need, alternatives, impacts, approver, decision and updated plan.
Common questions
When does a small request need formal approval?
Use the team’s change rules. Ask for a decision when a request changes an approved commitment, extends risk or requires a trade-off the working team cannot authorise.